All Township Residents:
The County Road 4 improvement project is substantially completed. (October 20, 2010) Approximately
3 miles of County Road (County State Aid Highway) #4 runs through our Town from about Red
Oak Road to the Breezy Point City Limits. The road project included a
total re-design and rebuild from Lakeshore Drive in Breezy Point to County
Road 18. This
is a State Aid highway and is therefore subject to State standards regarding
it's speed limit, signing and construction. The cost of the construction project was estimated to be between 3.1 and 3.8 million dollars but the winning bid came at $2.72 million, a savings of at least $350,000. The roadway was designed to 45 MPH specifications and a new speed study will be requested or MNDOT by the County when the new road is finished. Link to County Web Site information on C.R. 4 http://www.co.crow-wing.mn.us/highway/csah_4_project.html |